Home | Projects | The Shop | Contacts and Links | Guest Page | Family Stuff |
---|
Projects The Workshop
2/18/06 update 5/14/06, 5/22/06, 8/29/06, 9/12/07see
below Well the bug set in ... needed more space. The garage served well but just not enough room and no way to expand. Anytime I wanted to work on any project I had to move the cars and other things just to get to the machines. This was about a year ago, since then it has only gotten worse. So ... where to put a workshop, how big and the cost were the big questions. After much planning, the location became obvious. The size ... as big as possible of course! And the cost ... well that almost stopped the project. There had to be a lower cost method and after a few months of looking we found it. A company call Tuff Shed with a local office a few miles down the road. This is not a shed (although they do have them) it is a full up 24x16' garage with 2x4 studs on 16" centers, rafters at 24" centers, a man door and a 7' wide garage door. Full engineering plans approved and inspected by the city. How much? With a concrete slab that also meets city requirements ... 1/3 the cost of a contractor to do the same job. I would do all the electrical, insulation, drywall and inside/outside painting ... more savings! Now the time line ... hold on to your hat as now things really begin to move. After deciding the final size and door locations it took Tuff Shed 2 weeks for the plans, the city took 3 days to approve. A few days later the cement contractor started and took 4 days to remove an existing slab and spa, dig footing, lay rebar and pour cement. He started on Monday finished on Friday with a day for footing inspection and he is done. Tuff Shed started the next Wednesday and finished (all they could) a day and half later. Another inspection, we painted, they came back a few days later to finish the roof and they are done. A new workshop build in 3 weeks! But wait ... it's my turn. Now things really begin to slow down. Here's what I have done to date and need to do before move in: Pull a 240v (3 wire 6awg) 60 amp line from main power panel to a sub-panel in the workshop. DONE. Gets some lights in the place ... see what I'm doing. DONE. Pull from the sub-panel lines for outlets, lights and 240 at various locations around the shop. In process should finish in about another week. Install insulation in ceiling and walls. Take a few days. Drywall a week or so. Paint 2-3 days. So move in day ... maybe early March! Of course this will delay my A3 project but it's well worth it! The following pictures show some of the details: |
Update 5/14/06 Well, it has been long time since my last update. I have been working on the workshop ... it has just been a slow project. I only work on it a few days a week, then only for 3 - 4 hours at a time. But progress has been made ... the following photos shows the details. |
Well the move is basically done with only a few things here
and there. Such as finish the lathe table by adding a back and drawers.
Clean and fix a few things on the lathe. Add additional lights and wire
them up. Bring plumbed water in so that I can wash my hands. Put a few
things on the wall to personalize the workshop ... etc. etc.
Oh and find new things to add!! This will be the last update on the workshop project. As with most projects it took a lot longer then I thought ... but the end result is well worth the time and effort..... thanks for viewing! Now back to the A3 Switcher!! |
Update
9/12/07 Well I thought that I would not update this page but guess what .... New Stuff came in ... |
![]() |
![]() |
|
Here they are ... an Acra
10 x 54" Mill with DRO and VFD and Acra Lathe 13x40! |
Tight squeeze ... but it
did fit! |
|
![]() |
![]() |
|
Unloading very simple and easy! | Across the lawn ... 3/4"
ply wood then a thin sheet of steel on top then roller bearings ...
smooth ride!! |
|
![]() |
![]() |
|
This mill weighs in at about 3000#. | Now it's the Lathe turn. |
|
![]() |
![]() |
|
Re-arranged the shop and it
fits just fine. I see the new mill got the Kurt vise already! |
Moved the 9x20 and the new
Lathe took over the old spot. |
|
![]() |
![]() |
|
Front panel showing all the speeds and thread positions ... also has a jog button and flood coolant pump on/off switch. | The VFD controller, the
silver box is the breaking resistor. Unit runs on 240 v and provides 3
phase to the Baldor motor. Run very nice! From about 50 RPMs to 5000
RPMs with just changing from Low to High gear. |
|
![]() |
![]() |
|
The low/high gear is just a
little too close to the edge. I think a small adjustment is in order. |
Notice the two pulley system to the gear box and the 120/127 gear. | |
![]() |
So far I'm very happy with the new
additions to the shop. I still use the Enco 9x20 a lot so I may keep it.
As for the mill ... so far I haven't used it except for embossing the
rivets for the A3 switcher. But I will probably keep it until I need the
space. It has done a great job and I'm sure I will find many uses. Will see what arrives in the shop next March after Westtec in LA. |
|
I removed all the oil and
sprayed kerosene to clean out all the little particles then put in new
clean oil. |
||
Back to TOP | ||
Projects The Workshop |
Home | Projects | The Shop | Contacts and Links | Guest Page | Family Stuff |
---|
Copyright 2004 thru 2012 Pat Hutcheson |