 |
|
 |
|
| This view is looking as you walk into the
shop. Patrick and Mckenna have already taken up a play spot! I
had better get going or they may take over! |
|
This view is from the big door opening
looking at the main entrance. Some power has been wired
in ... the right wall is where a workbench is going you can see
where the 120
power has been installed. |
|
| |
|
|
|
 |
|
 |
|
| Here is a close up of the main entrance. The
blue box is the outlet for the outside motion detector lights. The
switch, when turned off then back on, allows the lights to come on and stay on, rather then just
for 10 minutes or so. The dual switches on the left are for the
lights ... one for a single 2 bulb 8' section, the other switch
is for the 3 other 2 bulb 8' sections. |
|
As you can see the
insulation is here ... had to order it special for the 24" centers
(ceiling and rafters), it's R13 for 2x4's. |
|
| |
|
|
|
 |
|
 |
|
| Installed an emergency light in case power
goes out ... it gets very dark ... these will show me the way
out ... safely. The 2 blue boxes in the upper corner are power for a
TV and a cable outlet. |
|
Lots of insulation for the
rafters, ceiling and walls. The two flex conduit are for the 240
single phase. Put in junction boxes in case I have to install
additional outlets. As of now I have wiring that will handle two
50 amps circuits but I use a 40 amp circuit breaker. Plus three
30amp circuits with 20amp breakers for the lathe, mill and
future. Plenty of room for additional equipment and larger motors!
|
|
| |
|
|
|
 |
|
 |
|
| Finally installed some insulation. When I
ordered the 24" wide batts, I had to order 8 bundles ... a lot more then
I needed. So I just cut those extras down to fit the 16"
centers and I was done. |
|
Now the drywall. Carol and I
actually lifted those very heavy 4'x8'x5/8" sheets. Also notice
3 of the 4 banks of lights. Two are using the T8 bulbs with an
electronic ballast. The other two are magnetic using T12 bulbs
(110 watts each), but they have a very
loud hum, I may change those for the newer T8s. |
|
| |
|
|
|
 |
|
 |
|
| Drywall done and two coats of
mud. The 2'x2' hole in the ceiling is for a little storage area,
I placed a few pieces of plywood down before the drywall. |
|
There must be about 10 pounds of
screws and 90 pounds of mud and I still have a thin coat to put
on. Then I will spray on the texture for an orange peel look, then prime and paint. The
table will soon have my 9x20 sitting on it. Getting close! |
|
| Closer and
closer .... 5/22/06 |
|
|
|
 |
|
 |
|
| Looking at the north wall ... what a
difference the texture makes! |
|
The south wall or main entrance.
The final thin coat of mud was done earlier this week, then I
sprayed on the orange peel look. |
|
|
Update 08/29/06
Finally.... progress !!
A lot of work has been done ... just not reporting all those
changes ... until now. |
|
|
|
 |
|
 |
|
| Finally found my ceiling tile
... the real problem was finding enough boxes that did not have
damaged tile. Before installing I primed and gave the walls two
coats of white paint ... really makes the place look nice. After the tile we put two coats
of epoxy floor covering, that took about 2 weeks for washing,
etching and all the drying etc. But well worth the time and
cost. |
|
Now we are ready to start the move!!
First the 300 lb lathe. I use the tailstock to help balance the
lathe. The black steel cross member is to place the lathe on the
hoist legs as we transport it. |
|
| |
|
|
|
 |
|
 |
|
| This move turned out to be a one person move
... I was hoping the giant turtle would help pull the hoist, but
he would have nothing to do with the project! |
|
Ready to be installed on it's
new bench, the plywood under the hoist is to help preserve
the epoxy floor. |
|
| |
|
|
|
 |
|
 |
|
| Easy ... the hoist makes it so
nice. This and the next pictures provides a good look at the
epoxy floor ... nice and smooth, easy to clean! |
|
Now that the lathe is at home I
thought it was time to bring in the surface plate. Doing
preliminary leveling. |
|
| |
|
|
|
 |
|
 |
|
| Next .... the 600lb mill/drill.
I had already removed the stand because the boom on the hoist
was too high to get it out of the garage. Plus it was way too
top heavy ... even with the head moved to it's lowest position. |
|
The route to the workshop is the
same ... so here we are ready for the stand. This move
was definitely not a one man job ... Carol and I had to do a lot
of pulling and shoving to get it across the lawn (even with
plywood) ... but we did it by taking our time and planning
ahead. |
|
| |
|
|
|
 |
|
 |
|
| The move is nearly complete with only a few
things left. This is the North wall showing the single car garage
door as the big entrance for those items that won't fit through
the man door (read new equipment!). |
|
The East wall. New equipment
will be placed to the left of the mill/drill or anywhere else
for that matter. The surface plate is positioned close to the
mill/drill and lathe, being out in the open I can now use all 4 sides. |
|
| |
|
|
|
 |
|
 |
|
| Part of the East wall and the
South wall. Notice the sink in the corner. Now I won't
have to dirty up the kitchen! |
|
Finally the West wall. This old workbench was
built about 35 years ago. It very big and heavy. I plan on
replacing the top surface with new plywood and clean it up. |
|
Well the move is basically done with only
a few things here and there. Such as finish the lathe table by
adding a back and drawers. Clean and fix a few things on the
lathe. Add additional lights and wire them up. Bring
plumbed water in so that I can wash my hands. Put a few things on the
wall to personalize the workshop ... etc etc.
Oh and find new things to add!!
This will be the last update on the workshop project. As
with most projects it took a lot longer then I thought ... but
the end result is well worth the time and effort..... thanks for
viewing!
Now back to the A3 Switcher!! |
|
|
|
|
Update
9/12/07 |
|
| Well I thought
that I would not update this page but guess what .... New
Stuff came in ... |
 |
|
 |
|
|
Here they are ... an Acra 10 x 54" Mill with
DRO and VFD and Acra Lathe 13x40! |
|
Tight squeeze ... but it did fit! |
|
 |
|
 |
|
|
Unloading very simple and easy! |
|
Across the lawn ... 3/4" ply
wood then a thin sheet of steel on top then roller bearings ...
smooth ride!! |
|
 |
|
 |
|
|
This mill weighs in at about 3000#. |
|
Now it's the Lathe turn. |
|
 |
|
 |
|
|
Re-arranged the shop and it fits just fine. I
see the new mill got the Kurt vise already! |
|
Moved the 9x20 and the new Lathe took over
the old spot. |
|
 |
|
 |
|
|
Front panel showing all the speeds and thread
positions ... also has a jog button and flood coolant pump
on/off switch. |
|
The VFD controller, the silver box is the
breaking resistor. Unit runs on 240 v and provides 3 phase to
the Baldor motor. Run very nice! From about 50 RPMs to 5000 RPMs
with just changing from Low to High gear. |
|
 |
|
 |
|
|
The low/high gear is just a little too close
to the edge. I think a small adjustment is in order. |
|
Notice the two
pulley system to the gear box and the 120/127 gear. |
|
 |
|
So far I'm very happy with the new additions
to the shop. I still use the Enco 9x20 a lot so I may keep it.
As for the mill ... so far I haven't used it except for
embossing the rivets for the A3 switcher. But I will probably
keep it until I need the space. It has done a great job and I'm
sure I will find many uses.
Will see what arrives in the shop next March
after Westtec in LA. |
|
| I removed all the oil and sprayed kerosene to
clean out all the little particles then put in new clean oil. |
|
|
|
| |
|
|
|
|
Back to Top |
|
|
|